Water System Improvements

The City is undertaking water system improvements to the north east region of Maple Ridge over the next two years. These improvements and upgrades to water reservoirs and water pump stations will build in system redundancy, provide additional fire storage and respond to growth and new developments that the City is experiencing. The projects are as follows:

224 Street prv and flow meter chamber (224 Street and 127 Avenue) – The City is planning to install an underground Pressure Reducing Valve (PRV) Chamber and a Flow Meter Chamber. This installation will allow the City to connect to the new Metro Vancouver Maple Ridge Watermain West (MRWW) which was installed by Metro Vancouver in 2016. The PRV is required in order to reduce Metro Vancouver’s high pressure to the City’s watermain typical operational pressure. The two vault chambers will be installed on the east side of 224 Street across from 127 Avenue. Traffic impacts will be minimal, however one lane alternating traffic may be required at times. The construction is expected to be completed by end of June 2018.

263 Street Pump Station Replacement

– The City is proceeding with the replacement of the 263 Street Water Pump Station at 26285 Dewdney Trunk Road. There is already an existing pump station and concrete water reservoir on the property with the new pump station being constructed to the south of the adjacent reservoir. The new pump station will be connected to the reservoir and the existing station decommissioned. The work generally consists of site clearing, minor water main installation, a new building to house the pump room, electrical room and the on-site chlorine generation system. The project will also include provisions to accommodate two new water reservoirs in the next 10-15 years to replace the existing concrete reservoir and add additional storage capacity. 

The contract has been awarded to Drake Excavating Ltd. and construction commenced at the beginning of September 2017. Project completion is scheduled for summer 2018. Traffic impacts will be minimal and should be limited to construction traffic/trucks turning off Dewdney Trunk Road. No work will take place on Dewdney Trunk and no road closures are expected.


270A STREET RESERVOIR and pump station 

– The City is proceeding with the installation of a second water reservoir and replacement of the 270A Street Water Pump Station at 12330 270A Street. There is already an existing pump station and bolted steel water reservoir on the property with the new pump station being constructed to the north-east of the existing pump station and the new reservoir to the east of the new pump station. The new pump station will be connected to the new and existing reservoirs and the existing station will be demolished. The work generally consists of site clearing, water main installation, a new pump station, and a new bolted glass-fused-to-steel reservoir. The project will also include provisions to accommodate a new water reservoir in the future to replace the existing reservoir. 

The contact has been awarded to WestPro, a Division of Pomerleau Inc. and construction is anticipated to commence in February 2018 with completion near the end of 2018.Traffic impacts will be minimal and should be limited to trucks accessing the site from the 270A Street cul-de-sac. Minor watermain work will be required in the 270A Street road right-of-way but no impacts to property access are anticipated. 

MCNUTT ROAD RESERVOIR – TANK 2

  - the new 1.0 million litre bolted steel tank is now operational with only minor deficiencies remaining on the project.